Port Botany Expansion (PBE), which won the Australian Construction Achievement Award in 2012, is a $1bn infrastructure project in New South Wales, Australia. The PBE project primarily involved the construction of a new terminal (Terminal 3) on 60ha of reclaimed land adjacent to the existing Patrick Terminal at Port Botany.
The approval for the construction of the new terminal at Port Botany was obtained in 2005 and construction began in July 2008. The first phase of the expansion was carried out by a consortium comprising Baulderstone and Jan De Nul. The port is owned by Sydney Ports Corporation.
The construction works of phase two of the project were carried out by Laing O’Rourke. Phase two became operational in 2014. The terminal expansion increased the port’s freight capacity to 1.6 million TEUs a year.
The new terminal generated up to 2,000 temporary jobs during construction and 1,900 permanent jobs upon commissioning. The terminal is also expected to add approximately $800m a year to the NSW economy. The new terminal is designed for a life expectancy of 100 years.
Construction details of Port Botany Expansion (PBE) phase 1
Phase one of the PBE project involved the reclamation of 63ha of land, construction of five new berths, and new wharves measuring 1,850m in length and 16.5m-deep. The phase also witnessed the construction of 216 precast retaining walls.
Related project
Port of Melbourne, Australia
The Port of Melbourne, on the mouth of the Yarra River, Victoria, Australia, is owned by the state’s Port of Melbourne Corporation.
Initial dredging activities were conducted by installing a silt curtain around the bay area to confine the sediment. The dredging works were first carried out using a dredging vessel named Nu Bounty. Up to 90,000m³ of concrete and 15,000t of steel is estimated to have been utilised for the construction of the terminal.
Project activities completed in 2011 under phase one involved the construction of rail and road links, dredging of approximately 7.8 million cubic metres of fill materials for the shipping channels and berth boxes, construction of a 200m tug berth, and installation of additional rail sidings. The works also involved improvement of the estuarine environment, construction of a new four-lane boat ramp comprising of pontoons, and construction of car parking areas.
An elevated road network in Penrhyn Road was also constructed as part of phase one. It involved the construction of an intersection, three access ramps, and four bridge spans. The road network was constructed to provide access to trucks at the existing Brotherson Dock. A pedestrian bridge over the Port Botany freight rail line at Banksia Street was also constructed as part of the project.
PBE Phase 2 construction details
Phase two of the PBE project involved the selection of a stevedore for the terminal to carry out the development and operation works. Hutchison Port Holdings (HPH) was selected as the contractor in 2009. HPH further subcontracted Laing O’Rourke to carry out the civil and rail works for the project.
Construction works under the Sydney Port Botany Terminal (SPBT3), which forms the first stage of phase two of the PBE project, were started in October 2012. The works involved paving of the internal road and rail facilities, installation of the container handling equipment, construction of the terminal buildings, construction of drainage facilities for which stormwater quality improvement devices (SQIDs) were installed, electrical works, and other ancillary activities.
A concrete batching plant was also constructed to facilitate the construction works.
Key players
Geotechnical engineering services and major design works for the project were provided by Golder Associates.
URS Global provided the design for the large gravity structures that form the quay walls, a 2,000m continuous cope beam, continuous rear crane rail beams and pile supporting system, navigational aids, boat ramp facility, foreshore revetments and breakwaters.
Asciano was contracted to deliver 44 of its patented AutoStrad® automated straddle carriers, which operate unmanned using radar and laser guidance technology for navigation.
Related content
Drydocks World Dubai Shipyard, United Arab Emirates
Drydocks World Dubai shipyard is the largest ship repair facility in the Middle East.
Hyundai Heavy Industries Ulsan Shipyard, South Korea
Hyundai Heavy Industries (HHI) is one of the biggest ship construction companies in the world.
Jebel Ali Port, Dubai, United Arab Emirates
Jebel Ali Port, located at Jebel Ali free zone, about 35km south-west of Dubai, is currently undergoing expansion work on Terminal 2 (T2).